Environmental assessment cost and time: every published figure, 2026

An environmental assessment under NEPA typically cost $5,000 to $200,000 in the only government-wide estimate (CEQ's 2003 task force), and took 9.6 months on average at DOT for EAs started and finished in 2021 to 2023. Since June 2023 the law caps one at 75 pages and a year.

Published November 16, 2026 · Updated November 16, 2026. Sources: GAO-14-369 (2014), CEQ (January 2025), DOE quarterly reports (2016, 2017), Resources for the Future (2025), the U.S. Code and the Federal Register, all read November 16, 2026. Download the CSV (51 rows).

What are the headline figures for an environmental assessment?

The headline figures for an environmental assessment are a 75-page, one-year legal limit and measured costs and times from four public sources, the newest covering 2021 to 2023.

$5k–$200kTypical EA cost, CEQ task force, 2003 (GAO, 2014)
$65,000Median DOE contractor cost per EA, 2003–2012
9.6 monthsAverage DOT EA started and finished 2021–2023 (CEQ, 2025)
20 monthsMedian DOE EA, 21 EAs, year to June 30, 2016
75 pagesEA limit since June 3, 2023, citations and appendices excluded
1 yearEA deadline; 180 days if the sponsor pays 125% of cost

What does an environmental assessment cost?

An environmental assessment cost $5,000 to $200,000 in the only government-wide estimate, from a 2003 CEQ task force that GAO quoted in 2014; small EAs ran $5,000 to $20,000 and large ones $50,000 to $200,000. Of the agencies GAO reviewed, only DOE tracked EA costs, and only what it paid contractors.

FigureValuePeriodSource
Typical EA, government-wide estimate$5,000–$200,0002003CEQ task force, via GAO-14-369
DOE contractor cost per EA, median$65,000 (range $3,000–$1.2M)2003–2012GAO-14-369
DOE EAs, median (8 EAs)$73,000 (average $301,000)Year to Dec 31, 2013GAO-14-369
DOE EAs, median (15 EAs)$200,000 (average $406,000)Year to Jun 30, 2016DOE quarterly report, Sep 2016
DOE EAs, median (6 EAs)$65,000 (average $139,000)Year to Mar 31, 2017DOE quarterly report, Jun 2017
For comparison: typical EIS$250,000–$2 million2003CEQ task force, via GAO-14-369
DOE counts what it pays contractors, not its own staff time (GAO-14-369). Read November 16, 2026.

How long does an environmental assessment take?

An environmental assessment took 9.6 months on average at DOT for EAs started and finished in 2021 to 2023, the newest measure; the others in the table run from about 4 months at the Office of Surface Mining to just under 23 months for solar EAs in 2009 to 2023. The law now allows one year.

Agency or setTimePeriodSource
DOT EAs9.6 months, average2021–2023CEQ, Jan 2025
Solar EAs, 19Under 23 months to FONSI, average2009–2023RFF, 2025
Geothermal EAs, 1214 months to FONSI, average2009–2023RFF, 2025
DOE EAs, 1114 months, medianYear to Mar 31, 2017DOE, Jun 2017
DOE EAs, 2120 months, medianYear to Jun 30, 2016DOE, Sep 2016
Forest Service EAs, 501About 18 months, averageFY2012GAO-14-369
DOE EAs13 months average, 9 median2003–2012GAO-14-369
Office of Surface Mining EAsAbout 4 monthsAs of 2014GAO-14-369
For comparison, the median EIS took 2.2 years from notice of intent to final in 2024, down from 3.6 in 2019 (CEQ, January 2025). Read November 16, 2026.

RFF found 13 of the 19 solar EAs and 8 of the 12 geothermal EAs took more than a year, the limit that has applied since 2023.

How common is an environmental assessment compared with a CE or an EIS?

An environmental assessment is the middle level of NEPA review and a small share of it: CEQ estimated that under 5% of NEPA reviews are EAs, about 95% categorical exclusions and under 1% EISs (GAO-14-369, 2014). The Forest Service's mix in fiscal 2008 to 2012 was 20% EAs of 14,574 reviews; DOE's was 2.6%. How the three levels differ is in EA vs EIS.

What does each route to an environmental assessment cost in 2026?

An environmental assessment can start free: EPA's NEPAssist and the Fish and Wildlife Service's IPaC cost nothing, and a sponsor may draft its own EA under the agency's supervision. Prices read on each provider's page November 16, 2026:

RoutePriceWhat it covers
NEPAssist, IPaCFreeScreening and species lists
ePlanOpening free; $49 a document in full, with Word; Pro $49/monthA draft EA and FONSI ($49.99 in app stores)
PNNL PermitAINot soldServices for federal agencies
ConsultantBy quoteStudies and the EA; see the costs above
CEQ opt-in fee125% of anticipated costA 180-day deadline

Which NEPA procedures does each agency use for an environmental assessment in 2026?

An environmental assessment in 2026 follows its lead agency's own NEPA procedures, because CEQ's regulations were removed effective April 11, 2025. The latest rule or proposed rule for each (corrections aside), from a Federal Register search on November 16, 2026:

AgencyLatest actionCitation
CEQ (40 CFR 1500–1508)Removal final Jan 8, 202691 FR 618
USDA (7 CFR part 1b)Final rule Apr 3, 202691 FR 17062
Interior (43 CFR part 46)Final rule Feb 24, 202691 FR 8738
FHWA, FRA, FTA (23 CFR 771)Final rule Sep 1, 202691 FR 56029
Energy (10 CFR 1021)Interim final Jul 3, 202590 FR 29676
Army CorpsInterim final Jul 3, 202590 FR 29461, 29465
HUD (24 CFR 50)Interim final May 22, 202691 FR 30209
EPA (40 CFR part 6)Proposed Jun 25, 202691 FR 38359
Forest Service objectionsFinal Oct 13, 202691 FR 64760
Six more (TVA, VA, NASA, NRC, STB, Postal Service) are in the CSV. CEQ keeps a directory of agency procedures.

What does this environmental assessment data not show?

This environmental assessment data does not show a current, government-wide cost or time: GAO titled its 2014 report "Little Information Exists on NEPA Analyses", and no newer source we found counts EAs across agencies.

  • No figure measures EAs finished under the 2023 limits; the newest EA timing covers 2021 to 2023.
  • Costs are DOE's or the 2003 estimate; consultants publish no fees, and agency staff time is not counted.
  • The DOE samples are small (6 to 21 EAs a year), so medians move a lot.
  • Timing differs: DOE counts from the EA determination to the final EA, RFF from the start of agency review to the FONSI.

How were these figures gathered?

These figures were gathered by reading each source itself on November 16, 2026: GAO-14-369 (April 2014); CEQ's EIS timelines report (January 13, 2025); DOE's quarterly reports for September 2016 and June 2017; Resources for the Future's How Long Does It Take? (2025); 42 U.S.C. 4336a and 4336f; and the Federal Register's API for each agency rule. Each row of the CSV carries its source link, period and read date.

How do you cite this data?

Cite this data as follows; the figures are free to reuse with the citation.

Winding AI, Inc. "Environmental assessment cost and time: every published figure, 2026." nepaenvironmentalassessment.com, November 16, 2026. https://nepaenvironmentalassessment.com/environmental-assessment-time-and-cost-2026/

Download environmental-assessment-time-and-cost-2026.csv: 51 rows (category, measure, value, unit, scope, period, source, source URL, date read).

How was this page checked?

Every figure was read in its source on November 16, 2026, and each one quoted on the home page or in EA vs EIS carries the same year. ePlan's prices come from eplan.ai/pricing the same day; ePlan is made by Winding AI, Inc., this site's publisher. Corrections: support@winding.ai.