NEPA environmental assessment: what goes in it, and who can write it

A NEPA environmental assessment (EA) is the concise public document a federal agency prepares to decide between a finding of no significant impact (FONSI) and a full environmental impact statement (EIS).

Since June 3, 2023, the law caps an EA at 75 pages and one year, and lets the project sponsor draft it under the agency's supervision. CEQ's old regulations are gone: each agency's own procedures now set the format.

Published November 16, 2026 · Updated November 16, 2026

In one line: the lead agency decides and signs; you can screen the site free, draft the EA yourself, start from an AI draft, or hire a consultant.
At a glance

How do the ways to get a NEPA environmental assessment written compare?

A NEPA environmental assessment can be screened with free federal tools, drafted by the project sponsor, started from an AI draft, written by a consultant or by agency staff, and sped up with CEQ's fee.

Prices read November 16, 2026; the fee, which buys time rather than writing, is last.

RouteWhat you getWrites your EAPriceWho answers for it
EPA NEPAssist + USFWS IPaCSite screens and a species listNo screens onlyFreeYou, then the agency
Write it yourself (sponsor)Your draft in the agency's formatYes you doFree, your timeThe agency evaluates and signs
ePlanA cited draft EA, then a FONSIA draft marked to checkOpening free; $49 a documentThe agency evaluates and signs
PNNL PermitAIAI services for agency staffNo agencies onlyNot soldThe agency
Environmental consultantThe EA, surveys and consultationsYesBy quote; $5,000–$200,000 typical (2003)The agency evaluates and signs
Lead agency staffThe agency's own EAYes for its own actionsFree for its own actions; cost recovery may applyThe agency
CEQ opt-in feeA 180-day deadlineNo adds speed125% of the anticipated costThe agency
The limits

What are the limits on a NEPA environmental assessment in 2026?

A NEPA environmental assessment may run 75 pages and must be finished within one year, under amendments the Fiscal Responsibility Act made on June 3, 2023; a sponsor who pays a fee can shorten that to 180 days.

Read in the U.S. Code and the Federal Register, November 16, 2026.

75pages at mostNot counting citations or appendices. An EIS gets 150, or 300 if extraordinarily complex. 42 U.S.C. 4336a(e).
1 yearto finishFrom the earliest of the agency's decision that an EA is needed, a complete right-of-way application, or its notice of intent. 4336a(g).
180 daysif the sponsor paysA fee of 125% of the anticipated cost, added July 4, 2025 by Pub. L. 119-21. 42 U.S.C. 4336f.
0CEQ regulations left40 CFR 1500 to 1508 removed effective April 11, 2025 (90 FR 10610); final rule January 8, 2026 (91 FR 618).
The template

What goes in a NEPA environmental assessment?

A NEPA environmental assessment holds a statement of purpose and need, the proposed action and any alternatives with the effects of taking no action, the affected environment and reasonably foreseeable effects, and the agencies and people consulted.

The outline follows the statute and USDA's procedures (7 CFR 1b.5, final April 3, 2026), the most detailed current list of an EA's minimum elements; other agencies use the same parts in their own order.

Environmental Assessmentname of the proposed action · lead agency · month year
  1. Cover and responsibility

    Lead agency agency, office; cooperating agencies if any; responsible official name, title; preparer agency, sponsor or contractor; unique identification number ID.

    USDA 7 CFR 1b.5(c)(7) requires the ID; a sponsor or contractor also files a statement of any interest in the outcome (1b.10).

  2. Purpose and need

    Agency proposes to action at location. It is needed because the problem, in one sentence. Its purpose is to outcome.

    Every environmental document needs a brief one (42 U.S.C. 4336a(d)).

  3. Proposed action, alternatives and no action

    The work includes each activity, size, method, timing. Alternatives considered: or why none were needed. Without the action, expected future condition.

    Alternatives are required where resource uses conflict (42 U.S.C. 4332(2)(H)); the consequences of no action are always described (7 CFR 1b.5(c)(2)).

  4. Affected environment and effects

    For each resource water, species, cultural sites, air, people…: today's condition, then the reasonably foreseeable effects, short and long term, beneficial and adverse.

    Significance turns on "reasonably foreseeable" effects (42 U.S.C. 4336(b)); USDA lists health and safety, economic and quality-of-life effects (1b.2(f)(3)).

  5. Mitigation and monitoring

    Measures the decision relies on: measure, who, when, under what authority.

    A FONSI that rests on mitigation must state its authority and any monitoring (7 CFR 1b.6(b)).

  6. Other laws and consultations

    Endangered Species Act finding; historic properties, NHPA Section 106 finding; Clean Water Act permit; others as the agency asks.

    One of USDA's minimum elements (7 CFR 1b.5(c)(5)).

  7. Agencies and persons consulted

    Agency or tribe, contact, date, how.

    A succinct list (7 CFR 1b.5(c)(4)).

  8. Page-limit and deadline certification

    "This EA addresses the factors NEPA requires within 75 pages and by deadline."

    USDA requires both (7 CFR 1b.5(c)(6)); pages are 8.5 by 11, one-inch margins, 12-point single-spaced.

  9. Citations, appendices and the draft FONSI

    Maps, data tables and studies list; then the FONSI: the selected alternative, why effects are not significant, when work starts, date and signature.

    Appendices sit outside the 75 pages but may not add analysis (1b.5(d)(2)).

Agencies differ in their order and extras: check yours in CEQ's directory of agency NEPA procedures. How an EA differs from an EIS, and what a FONSI is, are in EA vs EIS.

The routes

Who can write a NEPA environmental assessment, and what does each route cost?

A NEPA environmental assessment can be written by the agency, the project sponsor or anyone the sponsor hires, because since 2023 the law makes every lead agency allow sponsor preparation under its supervision (42 U.S.C. 4336a(f)).

One card per route, in the table's order; prices read on each route's own page November 16, 2026. Cost and time figures are on the 2026 data page.

1N

EPA NEPAssist and USFWS IPaC

Best for a free first screen

NEPAssist screens EPA's environmental data for an area you draw. IPaC lists the listed species, critical habitat, migratory birds and wetlands that may be affected, with suggested conservation measures.

Price: free; IPaC says it is open to anyone, public or private.

Good

  • Official federal data, no account for NEPAssist
  • Finds issues before you write

Watch out

  • Writes no EA text
  • A screen, not a finding: the analysis is still yours
Visit NEPAssist
2S

Write it yourself as the project sponsor

Best for small projects with a clear format

Since June 3, 2023, every lead agency must let a project sponsor prepare its EA under supervision. You follow the agency's format; the agency independently evaluates the draft and signs the decision.

Price: free, apart from your time and any studies the effects need.

Good

  • You control the words and the schedule
  • No fee for the document

Watch out

  • You research every resource section
  • USDA wants a statement of your interest in the outcome
Read 42 U.S.C. 4336a(f)
3e

ePlan

Best for a cited first draft at a set price

Describe the project and attach plans, maps and past letters. ePlan looks up public data (NEPAssist, IPaC, wetland and FEMA flood maps) and drafts the EA section by section, modeled on a signed EA from the same agency and project type, with highlights to check and fill in. A draft FONSI comes next.

Price: the opening of each draft (up to two sections) free; $49 for one document in full with its Word file; Pro $49 a month ($49.99 in the app stores).

Good

  • Read the opening of each draft before paying
  • EA, FONSI and CE memo from the same facts

Watch out

  • A draft: the agency evaluates it and signs
  • Runs no field surveys or agency consultations
Visit ePlan
4P

PNNL PermitAI

Built for federal reviewers

A Pacific Northwest National Laboratory platform of past NEPA documents and AI modules, funded by DOE and the Permitting Council, offered as services to agencies: finding past reviews, sorting comments, helping experts draft and screen CEs.

Price: no subscription or price for applicants, since it isn't sold to them; agencies get it as a government-funded service.

Good

  • Built on millions of pages of past reviews
  • Government-funded, for the reviewers

Watch out

  • An applicant can't buy or use it
  • Helps the agency's staff, not your draft
Visit PermitAI
5C

Environmental consultant

Best for surveys and contested projects

A consulting firm writes the EA and runs the studies behind it: species and cultural surveys, wetland delineation, modelling and agency meetings. The agency still evaluates it.

Price: by quote. CEQ's 2003 task force put a typical EA at $5,000 to $200,000; DOE's contractor-prepared EAs had a median cost of $65,000 in 2003 to 2012 (GAO, 2014).

Good

  • Studies, drafting and agency meetings in one
  • Knows your agency's reviewers

Watch out

  • The most expensive route
  • Few published prices; the figures are old
Read GAO's cost figures
6A

Lead agency staff

When the agency's own action needs one

For an agency's own action, such as a national forest's fuels project, its staff write the EA and the responsible official signs the FONSI. GAO found the Forest Service's 501 EAs in fiscal 2012 took about 18 months on average.

Price: free when it is the agency's own action; applicants may owe cost recovery, such as BLM's right-of-way processing fees (43 CFR 2804.14).

Good

  • The decider writes it
  • No cost to an outside sponsor

Watch out

  • Staffing sets the pace
  • Outsiders shape it only through comment and consultation
Find your agency's procedures
7F

CEQ project sponsor opt-in fee

Best when the schedule matters most

Since July 4, 2025, a sponsor can ask CEQ for a fee notice (due within 15 days) and pay it to have the EA finished within 180 days of payment instead of a year. It buys a deadline, not a writer.

Price: 125% of the anticipated cost to prepare the EA, or to supervise a sponsor-prepared one.

Good

  • A deadline written into the statute
  • Works with any route above

Watch out

  • A quarter more than the work's own cost
  • CEQ's 2025 guidance expects you to talk to the agency first
Read 42 U.S.C. 4336f
What changed

Which NEPA rules apply to an environmental assessment now?

A NEPA environmental assessment now follows the statute as amended in 2023 and 2025 and the lead agency's own procedures, because CEQ's regulations were removed effective April 11, 2025.

Each date read in its source on November 16, 2026.

  1. Fiscal Responsibility Act (Pub. L. 118-5) adds levels of review, the 75-page and one-year limits, sponsor preparation and a "major Federal action" definition.

  2. Marin Audubon v. FAA: a divided D.C. Circuit panel says CEQ had no authority to issue binding NEPA regulations.

  3. Executive Order 14154 revokes Executive Order 11991, the 1977 order behind CEQ's regulations.

  4. CEQ's regulations end: its interim final rule of February 25, 2025 (90 FR 10610) takes effect.

  5. Seven County Infrastructure Coalition v. Eagle County: the Supreme Court tells courts to give agencies substantial deference on the scope of their NEPA analysis.

  6. Agencies publish new procedures: Interior, USDA, Energy, FHWA/FRA/FTA, the Army Corps and FERC, mostly as interim final rules.

  7. Pub. L. 119-21 adds the sponsor fee: 125% of cost for an EA in 180 days (42 U.S.C. 4336f).

  8. CEQ's final rule confirms the removal (91 FR 618). Final agency rules follow: Interior February 24, USDA April 3, FHWA/FRA/FTA September 1, 2026.

Every agency's current procedure, with its Federal Register date, is in the 2026 EA data.

How to choose

How do you choose a route, and what are the steps of a NEPA environmental assessment?

A NEPA environmental assessment route follows from three questions: who must sign, how much of the analysis needs field work, and how tight the schedule is.

Who is the lead agency?

Its procedures set the format and the public notice (find yours).

Does it need field work?

Surveys or modelling point to a consultant; a paper review can start free or from a $49 draft.

Is one year too long?

The fee route sets 180 days for 125% of the cost; DOT's EAs averaged 9.6 months (2021 to 2023).

  1. Confirm NEPA applies: a "major Federal action" excludes, for one, a non-federal project with no or minimal federal funding (42 U.S.C. 4336e(10)).
  2. Check for a categorical exclusion: if the agency's own or an adopted one fits, no EA is needed (4336(a)).
  3. Agree the purpose and need and the schedule with the lead agency (4336a(a)(2)(D)).
  4. Screen the site with NEPAssist and IPaC, and start any ESA or Section 106 consultation early.
  5. Draft within 75 pages, data in appendices, using the sections above.
  6. Publish and notify as the procedures say: HUD 15 days on a FONSI notice, FHWA 30 days of availability, USDA on a website.
  7. Decide: a signed FONSI, or an EIS (EA vs EIS).
Guides

Where can you read more about NEPA environmental assessments?

A NEPA environmental assessment has two guides here so far, each built from the statute and agency records.

FAQ

What do people ask about NEPA environmental assessments?

What is a NEPA environmental assessment?

A NEPA environmental assessment (EA) is a concise public document a federal agency prepares for a proposed action that has no reasonably foreseeable significant effect on the human environment, or whose significance is unknown. It sets out the basis for a finding of no significant impact (FONSI) or for deciding that an environmental impact statement is needed (42 U.S.C. 4336(b)(2)).

How long can an environmental assessment be?

An environmental assessment may run 75 pages, not counting citations or appendices (42 U.S.C. 4336a(e)(2), added June 3, 2023). USDA also fixes the page: 8.5 by 11 inches, one-inch margins, 12-point single-spaced.

How long does a NEPA environmental assessment take?

A NEPA environmental assessment is due within one year of the earliest of the agency's decision that one is needed, a complete right-of-way application, or its notice of intent. A sponsor that pays CEQ's fee of 125% of the anticipated cost gets a 180-day deadline. DOT's EAs started and finished in 2021 to 2023 took 9.6 months on average.

Can the applicant write the environmental assessment?

Yes. Since 2023 every lead agency must have procedures that let a project sponsor prepare an EA under the agency's supervision; the agency must independently evaluate it and takes responsibility for its contents (42 U.S.C. 4336a(f)). Under FHWA, FRA and FTA rules the applicant prepares the EA in consultation with the agency (23 CFR 771.119).

Is there a public comment period for an environmental assessment?

NEPA itself sets no comment period for an environmental assessment; each agency's procedures do. HUD allows 15 days of comment on a published FONSI notice (24 CFR 58.45), FHWA, FRA and FTA keep an EA available for 30 days (23 CFR 771.119), and USDA leaves comment to the responsible official (7 CFR 1b.5).

What happens after an environmental assessment?

After an environmental assessment the agency either signs a finding of no significant impact, and the action can go ahead once the FONSI is published and the required notices are sent, or finds a reasonably foreseeable significant effect and prepares an environmental impact statement.

How was this page checked?

We read the statute (42 U.S.C. 4332 to 4336f), the CEQ and agency rules in the Federal Register and the eCFR, and Congress.gov's record for H.R. 4776 and S. 5653 on November 16, 2026, and each route's own page the same day. Time and cost figures, with their years, are on the 2026 EA data page. Not legal advice: the lead agency's procedures decide.